Copying a Schedule Forward

Notes:  


  1. Click on the toolbar.

The Employee Schedules window displays.

  1. In the Week Of field, select the week with the schedule you want to copy.

  2. Click Copy.

The Copy Week of window displays.

  1. Complete the following:

  1. In the Copy Schedule forward field, select the number of weeks ahead to copy the schedule forward.

  2. In the weeks beginning field, select the week from which to copy the schedule forward.

  3. Select the employee(s) for whom to copy schedules forward.

  1. Select one of the following options in the Copy Forward Criteria section:

  1. Complete the following as necessary:

  1. Select Do NOT overwrite or delete NON-WORK time (vacations, etc.) if you do not want to overwrite any scheduled "non-work time" work activities.

Note:  You can define a work activity as "non-work time" by deselecting Show as Work Time on the Work Activities window.

  1. Select Automatically overwrite existing schedule without prompting to overwrite any existing schedules defined for the employee.

  2. Select Delete 'work time' schedules that match criteria before copying new schedules to delete any existing schedules that have been defined for the employee during the date range in which you are copying schedules forward.

  1. Click Ok.

 

Copying a Daily Schedule to Another Employee

Copying a Weekly Schedule to Another Employee